One of the largest projects carried out by our engineering center is a complex transport interchange that has no analogues in the CIS, and is located at the intersection of Heydar Aliyev and Zia Buniyatov Avenues, Baku, Azerbaijan.
The transport interchange consists of:
The customer was the Ministry of Transport of Azerbaijan.
Stage I of the project:
Stage II of the project:
The distances between the metal arcs are different, and, accordingly, the heights of the axes also differ.
• I-th arc: L=68.83; Rox. = 27.61
• II-nd arc: L=65.08 m; Rh. = 26.12
It should be noted that this project included the design of an overpass with a length of the main span L = 56.0 m, suspended by parabolic metal arches.
Stage III of the project:
For the first time in Azerbaijan, our company has designed a cable-stayed overpass with a span length of 360.0 m and a pylon height from ground level of 98.0 m.